Concrete does not dry out like paint. It hardens through a chemical reaction between cement and water called hydration, and that reaction carries on for weeks. Understanding the difference between setting, curing and drying is what stops a slab being ruined in its first 48 hours.
Concrete can be set and still be nowhere near strong. It can also be strong and still be too wet to floor over. Which mix you started with changes all of it — see what concrete mix do I need.
As a guide for a general-purpose mix in ordinary British weather. Cold slows every figure down, sometimes dramatically.
| Stage | Typical timing | What it means |
|---|---|---|
| Initial set | 1–3 hours | The surface will no longer take an impression easily. Finishing work is done around this point. |
| Final set | About 6 hours | Stiff throughout. Too late to work the surface. |
| Foot traffic | 24–48 hours | Careful walking. Keep barrows, trestles and point loads off it. |
| Strike vertical formwork | 24–48 hours | Sides of a base or wall. Soffits and anything propped stay far longer — take that from the engineer. |
| Two thirds of strength | About 7 days | A useful rule of thumb rather than a guarantee. |
| Light vehicles | About 7 days | A car on a domestic driveway, if it has been cured properly. |
| Characteristic strength | 28 days | The figure the mix is specified against. Heavy plant and full design loads wait for this. |
| Dry enough to floor over | Far longer | Governed by drying, not strength — see below. |
Hydration is quick at first and then slows down, without ever quite stopping. The industry settled on 28 days as the age at which characteristic strength is measured because by then the great majority of the strength has developed and the remainder is slow enough not to matter for design. When we test cubes from a load, that is the age they are crushed at, alongside an earlier 7-day result as a check.
Below about 5°C hydration slows sharply, and near freezing it effectively stops. Fresh concrete that freezes before it has gained strength can be permanently damaged, because the water expands inside it. In cold weather, protect the pour: insulating blankets, covers, and leaving formwork on longer all help hold the heat the mix generates itself. Expect every timing in the table above to stretch, and tell the plant when you order — our ready mixed concrete can be batched to suit the conditions you are pouring in.
Heat, low humidity and wind pull moisture out of the surface faster than it can rise from below. That causes plastic shrinkage cracking — short, random cracks appearing within hours of the pour — and a weak, dusty surface. On a hot or breezy day, pour early, keep the surface covered between operations, and start curing as soon as you can.
Curing is not complicated. It is keeping the water in for the first few days:
If you are laying a floor finish, the number you need is not strength but residual moisture. Screeds and slabs both have to dry to a level the floor covering will tolerate, and that takes far longer than curing. Our guide to traditional and liquid screeds covers the drying rules and where they differ.